From KNEW Operations 2015-08-17: The contractor began the ramp repair project this morning on Sites A, B, and C. The estimated impact of this project is approximately 5-7 days, depending on weather.
All areas mentioned above were barricaded, flagged and lighted. All NOTAMS were issued to reflect the three work sites (Site A, B and C) until Tuesday, August 25th at 2200Z (reference NOTAM #08/025 for Site A, #08/023 for Site B, and #08/022 for Site C).
Saw cutting and some demolition began on Site A; the site will be completely excavated tomorrow with the plan to have both Site B and C completed by 1700L tomorrow (August 18th) or by COB on August 19th. The contractors were advised to have Site A poured first, if possible and then proceed with Site B and C. Saw cutting also began on Site C and should be completed by COB tomorrow (August 18th). The plan is to begin pouring concrete at all three sites by this Thursday or Friday.
All men and equipment are done for the day and will resume work tomorrow between 1230Z and 1300Z. The saw-cutting machine has been left inside the perimeter for Site A (pictured below) with a flag and light attached (indicated via the NOTAM referenced above).
ARFF will ensure all lights are in working order and the flags/barricades remain in place.
IMPORTANT:
In an effort to prevent possible damage or destruction of the work site, please be mindful of how aircraft are marshalled into the ramp area where the work sites are barricaded. Site C is located approximately 50FT from the taxiway centerline, which is south of the southern edge line of the taxiway.