The taxiway crack seal/sealcoat project is moving along as planned. The schedule as we know it right now is:
- Friday, Jan 30, 2015, and Saturday, Jan 31, 2015: Sections of Taxiway Foxtrot in front of Landmark and Flightline First are being prepped and sealcoated, arranged so that Landmark can get in and out via Taxiway Bravo (F closed from just east of B to Taxiway G) and Flightline First can get in and out to the west (F closed from Flightline First mid ramp to halfway across the Bastian Mitchell ramp). Everyone should have access to their ramps from one side or the other.
- The terminal ramp will be closed on Monday, February 2, 2015 and Tuesday, February 3, 2015. Please do not park any aircraft on the terminal ramp these days as there will be a movie shoot there. Please note that this is a change from the previous plans for Sunday and Monday.
- Monday, Feb 2, 2015: Sealcoat prep and work will continue on portions of Taxiway Foxtrot provided the previous sections of F are finished and open. Everyone will still have access to their ramps from one side or the other. We will make every attempt to keep you advised of the latest progress.
Thank you all, in advance, for your cooperation in getting our taxiways rejuvenated, which will prolong the life of the pavement and our airport.